Cubic Yard Calculator: Concrete Volume in Yards

Work out cubic yards from length, width and depth. Results in cubic yards, feet and metres, with a 10% waste buffer for ordering.

Area and depth

Enter the space you are filling.

Accepts 20ft 6in, 10' 6", 20.5, 4 1/2.

Enter length, width and depth to see the volume in cubic yards.

All calculations run in your browser — nothing is sent anywhere.

How to calculate cubic yards

yd³ = (length ft × width ft × depth ft) ÷ 27

Multiply length by width by depth with every measurement in feet, which gives cubic feet, then divide by 27 to get cubic yards. Depth is usually quoted in inches, so divide inches by 12 first — a 4 in slab is 0.333 ft.

Worked example: A 20 ft × 10 ft slab at 4 in deep is 20 × 10 × 0.333 = 66.7 ft³, and 66.7 ÷ 27 = 2.5 cubic yards.

Concrete, gravel, topsoil and mulch are all sold by the cubic yard in the United States, but nobody measures a slab in yards — you measure it in feet and inches. That mismatch is where ordering goes wrong. This calculator does the conversion and adds the 10% buffer you should be ordering to.

Cubic yards for common slab sizes

At the standard 4 in residential slab depth:

SlabAreaCubic yards
10 × 10 ft100 ft²1.23 yd³
12 × 12 ft144 ft²1.78 yd³
16 × 16 ft256 ft²3.16 yd³
20 × 20 ft400 ft²4.94 yd³
24 × 24 ft576 ft²7.11 yd³

Depth changes the answer proportionally: the same 20 × 20 ft slab at 6 in is 7.41 yd³ rather than 4.94. Half again the depth is half again the concrete, and it is the single easiest way to blow a budget without noticing.

Why 27

A yard is three feet, so a cubic yard is 3 × 3 × 3 = 27 cubic feet. It is a definition, not a measured conversion, so dividing cubic feet by 27 is exact. The number that trips people up is not 27 but the depth: a 4 in slab is 0.333 ft, not 4, and entering 4 gives an answer twelve times too large.

Ordering by the yard

Cubic yards for other materials

The arithmetic is identical for gravel, road base, topsoil and mulch — length × width × depth ÷ 27. What changes is the buffer and the depth convention. Loose materials settle and compact, so suppliers often suggest more than 10% for base course, and mulch is usually spread 2 to 3 in deep rather than 4.

Weight per yard differs sharply too, which matters for delivery: concrete is about 4,000 lb per cubic yard, dry gravel roughly 2,800 lb, and mulch only a few hundred.

Converting a figure you already have? Use the cubic feet to cubic yards converter. Buying in bags rather than by the truck? The concrete bag calculator turns a volume into a bag count. Once you know the volume, the concrete cost calculator applies your supplier’s rate.

For a shaped pour rather than a plain rectangle, the circular slab, circular column and post hole calculators handle the geometry for you.

Related concrete calculators

Pouring a different shape? These cover the rest of the common jobs.

Working out volumes on site?

This tool is web-only. The Concrete Calculator app covers the five volume calculators — rectangular and circular slabs, irregular slab area, circular columns and post holes — with saved projects, job history and full offline use.

Download on the App Store

Free · 4.8 ★ on the App Store

Frequently asked questions

How do I calculate cubic yards?
Multiply length × width × depth in feet to get cubic feet, then divide by 27. Depth in inches must be converted to feet first by dividing by 12, so a 4 in slab is 0.333 ft. A 20 × 10 ft slab at 4 in is 66.7 ft³, or 2.5 cubic yards.
How many cubic feet are in a cubic yard?
Exactly 27. A yard is 3 feet, and a cubic yard is 3 × 3 × 3, which is 27 cubic feet. That figure is a definition rather than a rounded conversion, so it never changes.
Why is concrete sold by the cubic yard?
In the United States ready-mix is batched and billed by the cubic yard, and mixer trucks are sized in yards — typically 8 to 11 per full load. Everywhere on the metric system it is sold by the cubic metre instead. One cubic yard is about 0.765 cubic metres.
How much does a cubic yard of concrete weigh?
Around 4,000 lb, or close to two short tons, for ordinary mixes at roughly 150 lb per cubic foot. This matters more for access than for ordering — a full truck is well over 20 tons, and soft ground, verges and service covers do not always survive one.
Should I order the exact figure?
No. Order the buffered figure. Subgrade is never perfectly flat, formwork bows, and some concrete is always lost in the chute. A short pour means either a cold joint or a second call-out, both of which cost far more than the extra 10%.